WATER RATES: 

Users located inside the Village limits 

For each single family or single business, professional, commercial or industrial connection inside the corporate limits of the Village the following rates apply:

0 to 100 cu ft  $9.89
101 to 6700 cu ft  $2.23 / 100 cu ft
6701 to 13000 cu ft $2.10 / 100 cu ft
13001 to 26000 cu ft $1.84 / 100 cu ft
Over 26000 cu ft $1.32 / 100 cu ft

  Users located outside the Village limits

0 to 100 cu ft $14.84
101 to 6700 cu ft $3.35 / 100 cu ft
6701 to 13000 cu ft $3.14 / 100 cu ft
13001 to 26000 cu ft $2.76 / 100 cu ft
Over 26000 cu ft $1.98 / 100 cu ft

 1 cubic foot = 7.48 gallons.

 For those industries with fire lines, the charges are as follows:

Line Size Quarterly Charge
2” $15.00
3” $25.00
4” $50.00
6” $87.50
8” $125.00
10” $195.00
12” $281.25

 SEWER RATES

Inside

0-200 cu ft $9.25 
Over 201 cu ft $2.78/100 cu ft

Outside

0-200 cu ft $13.88
over 201 cu ft $4.17 / 100 cu ft

 

WATER TAP FEES

Taps on the same side of the street as the water line are:

SIZE

INSIDE THE VILLAGE LIMITS OUTSIDE THE VILLAGE LIMITS
¾” $700.00 $1050.00
1” $950.00 $1425.00
1 ½” $2500.00  minimum $3750.00
2” $3300.00  minimum $4950.00

Taps requiring a bore under the street:

SIZE INSIDE THE VILLAGE LIMITS OUTSIDE THE VILLAGE LIMITS
¾” $850.00 $1275.00
1” $1100.00 $1650.00
1 ½” $2850.00 minimum $5130.00
2” $3800.00 minimum $5700.00

A duplex may use a minimum 1” tap for the two apartments.  Included are 2-3/4” meters, 2 valves, 2 curb boxes and a “y” fitting.

Fees are:

INSIDE OUTSIDE
$1250.00 $2500.00

 If a bore is required:

INSIDE OUTSIDE
$1400.00 $2700.00

 All larger taps are similarly priced and the Village office should be contacted for further information.  Additionally, for larger taps, a development fee is charged and this cost may be obtained from the Village office.

A front footage charge of $8.00 per front foot of the lot or land to be served by such a tap inside the Village is charged.  The outside footage charge is $12.00 per front foot with a minimum of 150’ charged outside the Village.